A 50,000 sqm utility installation shows how 3D excavator guidance cuts timelines by 30% and removes costly rework.
Scope
50,000 sqm utility installation
System
3D excavator guidance
Timeline
30% faster
Rework
Effectively eliminated
The job
Utility excavation demands depth accuracy around live services. Traditional practice means repeated manual checks, an exposed worker in the trench and frequent over-dig that must be backfilled and compacted again.
With 3D guidance
- Operator sees bucket position against design depth in real time.
- Trench profile achieved in fewer passes with no manual depth checks.
- As-dug data captured for records and billing.
Results
- 30% shorter programme on the excavation package.
- Over-dig and re-compaction costs largely removed.
- Improved trench safety through fewer people at the face.